Client: NLNG
Status: ONGOING
Installation Supervision of the following activities
1.) Full decommissioning of existing old Mark6 Turbine control system
2.)
Removal of old panel and positioning of the new one are at Company’s care, as per Matrix of Responsibility. Upgrade of Water wash panel and
integration to Mark VIe
3.) Interface and integration check activities with DCS and Fire and Gas systems
4.) Commissioning and
start-up of the upgraded Mark Vie turbine control Systems
5.) As Built’ drawings and documentation
Client: NLNG
Status: COMPLETED
Install, supervise and commission a fully functional ten (10) units of
Mark Vie Triple Modular Redundant (TMR) turbine controller;
EX2100e
generator excitation systems; additional functionality for Hazardous
gas, Switches to transmitters upgrade and water wash
PLC
integration; Servers and Network switches of General Electric (GE) Gas
Turbine Generators.
Client: WRPC
Status: COMPLETED
Filter House Maintenance, Exhaust System, Duct, Diffuser, Baffles And
Silencers Reconstruction, Compressor and Casing
Repairs Provision
for Hotel Accommodation, Transportation and Shipping of Parts To Site,
Workmanship
Client: WRPC
Status: ONGOING
Major Inspection spares of Gas Turbines 1 & 2 for WRPC – Warri Refining and Petrochemical Company
Client: WRPC
Status: COMPLETED
Supply of G.E certified instrumentation spares as follows:
Client: WRPC
Status: COMPLETED
Client: OCTOLIT
Status: COMPLETED
Complete Supply of Gas Turbine Parts
Client: CMEC
Status: COMPLETED
Complete Supply Turbine Spare Parts for the Omotosho Simple Cycle 500mw Phase II